Challenge:
- Multiple cross contamination by hydrocarbons & heavy metals, among clean.
Solutions:
- Executive design carried out by SARPI Remediation.
- Excavation of 1,2M m³ of material.
- On site soil treatment by washing within a large plant designed, constructed & operated by SARPI Remediation.
- On site material reuse after treatment.
- Evacuation of 300.000 tonnes of material not compatible with human health criteria.
- Groundwater treatment: In situ groundwater remediation by ZVI and Pump & Treat for chlorinated compounds. 170m³/h flow rate.
- Organisation: JV with civil works & land remediation company Semp.